Apollo Atomics

Apollo Atomics

We make the most compact nuclear machines.

Let's Build It · Apollo Atomics launch video[4]

$10M

Seed round (raising)

Earmarked for the A-1 MW-scale facility

40x

More compact than a conventional plant

One component changed: the steam generator

2028

NRC construction permit target

Pre-application docket 99902160

Backed by Y Combinator (P26, group partner Tom Blomfield) and Orange Collective, alongside Genesis Fund, Intuition, New Era Ventures, Paperjet Ventures, and the US National Science Foundation.[7]

Thesis

AI has turned firm power into the scarcest commodity in tech, and nuclear is the only clean source that ships it 24/7 — but the nuclear playbook takes a decade per plant. Apollo changes exactly one component, the steam generator, and gets a reactor 40x smaller that keeps everything the NRC has already licensed dozens of times.[2]
  1. 01

    The demand is contracted, not hypothetical. In twenty months, Microsoft, Google, Amazon, and Meta signed roughly 16 GW of nuclear supply deals — and IEA counts 20+ GW of SMRs that tech companies plan to finance. Customers who need power in 2030 are being told to wait until 2035.[14] [16] [20]

  2. 02

    One component changed, everything else proven. The Compact Steam Generator is 20x smaller at the same thermal power, shrinking the full plant ~40x — while keeping the pressurized water reactor design that runs ~80% of the world's nuclear fleet, light water coolant, and standard low-enriched uranium. Every funded competitor of note is betting on a new reactor type; Apollo is betting on a heat exchanger.[2] [4]

  3. 03

    The supply chain already exists. Fuel is off the shelf from Framatome and Westinghouse, while HALEU-dependent competitors are queued behind an enrichment supply that has produced ~920 kg to date — a constraint that already delayed TerraPower's Natrium by two years. BWXT, Siemens Energy, ABB, and Framatome are under commercial agreements for the rest.[26] [31] [32]

  4. 04

    Regulation just flipped from headwind to tailwind. EO 14300 caps new-reactor licensing decisions at 18 months, Part 53 became a final rule in April 2026, and the NRC is already running reviews on 9–17-month schedules. Apollo's regulatory engagement plan for the A-10 is docketed (ML26092A282), targeting a construction permit by 2028.[5] [8] [11] [12]

  5. 05

    The rare team that has operated, designed, and manufactured. Assil spent a decade across EDF's SMR design team, reactor operations in Belgium, and an MIT PhD that spins out 15+ years of compact-steam-generator research under Prof. Koroush Shirvan. Drew scaled manufacturing at electric truck and boat companies after 3.5 years of White House operations; the head of manufacturing built battery lines at Tesla and Rivian and built Apollo's test reactor at MIT.[36] [37] [38]

Problem

Everyone wants nuclear. Nobody can have it on time.

Data center electricity demand roughly doubles to ~945 TWh by 2030 on IEA numbers; Goldman pegs the growth at +165% versus 2023. The hyperscalers have already decided nuclear is the answer for firm, clean power — that part of the debate is over.[13] [15]

The problem is the clock. Gigawatt-scale nuclear takes 10+ years and ~$20B per plant. Most SMRs in development rely on exotic fuels, unproven coolants, or supply chains that don't exist yet — credible delivery dates start in the 2030s. And the fast fossil alternative is gone: gas turbines are effectively sold out through 2030.[2] [33]

Customers with 2028–2035 power needs — data centers, industrial heat users, utilities — have demand today and no nuclear option that ships on their timeline.[2]

Data center electricity demand roughly doubles by 2030

Chart

Global data center electricity consumption, TWh. Endpoints are IEA Energy & AI estimates (~415 TWh in 2024 to ~945 TWh by 2030); intermediate years interpolated at the implied ~14.7% CAGR.

Source · IEA, Energy & AI (2025)

10+ yrs

Conventional gigawatt build

~$20B per plant

2030

Gas turbines sold out through

~80 GW GE Vernova backlog, ~3-yr lead times

2035+

Most SMR delivery dates

Exotic fuels and supply chains still unbuilt

[2] [33]

Why Nuclear, Why Now

The buyers, the government, and the regulator all moved within 20 months.

Three independent forces converged: hyperscalers signing gigawatt-scale nuclear PPAs, a 400 GW national capacity target, and the fastest NRC reform in the agency's history.

Hyperscalers contracted ~16 GW of nuclear in 20 months

Chart

Announced or contracted capacity per deal. Microsoft–Constellation Crane restart (835 MW, Sep 2024); Google–Kairos (500 MW by 2035); Amazon–X-energy (5 GW by 2039); Meta–Constellation Clinton (1.1 GW); Amazon–Talen Susquehanna (1.92 GW through 2042, ~$18B); Meta's Prometheus deals with Oklo, TerraPower, and Vistra (up to 6.6 GW by 2035).

Source · Constellation · Kairos · POWER · Talen · CNBC · Utility Dive (2024–2026)

[16] [17] [18] [19] [20] [21]

Washington rewired the rules in one year.

May 23, 2025. Four executive orders set a national target of quadrupling nuclear capacity from ~100 GW to 400 GW by 2050. EO 14300 ordered the NRC to decide new-reactor applications within 18 months and license renewals within 12 — with a wholesale rewrite of its regulations on an 18-month deadline.[8] [9]

March–April 2026. Part 53 — the first technology-inclusive, risk-informed licensing framework — became a final rule, effective April 29. A companion proposed rule lets the NRC directly leverage DOE-authorized test reactor results in commercial reviews. The agency is already running real dockets on 9–17-month schedules, and TerraPower received the first commercial advanced-reactor construction permit in decades.[11] [12] [25] [44]

One year in. DOE's own retrospective: 11 reactor pilot projects selected, the DOME test bed open at Idaho National Lab, $2.7B committed to restoring enrichment capability, and 31+ countries signed onto tripling global nuclear capacity by 2050.[10] [39]

Energy infrastructure now demands reliability, rapid deployment, and strict cost discipline more than ever before.
Assil Halimi, announcing the MIT NSE collaboration[6]

The Compact Steam Generator

Change one part. Shrink the whole plant 40x.

The steam generator is the physically dominant component of a pressurized water reactor — and the only one Apollo touches.

The steam generator is why nuclear plants are buildings instead of machines.

A commercial PWR steam generator stands up to 70 feet tall, weighs 300–800 tonnes, and contains thousands of hand-assembled U-tubes; a plant needs two to six of them. They are among the largest and most expensive hand-built components in all of industry — and their size dictates the containment building, the construction schedule, and ultimately the decade-long timeline.[35]

Apollo's Compact Steam Generator replaces that vessel with a component 20x smaller at the same thermal power — per the launch video, "thousands of needles through 5% of the space" — cutting the plant's overall footprint by ~80% in volume terms and making the full system roughly 40x more compact: pre-tested, factory-built, transportable, and contracted at a fixed price.[2] [4]

Everything else stays inside the NRC's comfort zone: light water, standard low-enriched uranium, fuel and components from existing qualified supply chains, and the PWR architecture backed by 15,000+ reactor-years of global operating experience.[2] [7]

300 MW

Apollo's largest truck-transportable unit

A-300, targeted 2031

70 MW

Next closest transportable competitor

Most of the market sits at ~10 MW

<24 mo

Target deployment time

Versus 10+ years for conventional builds

[2] [4]

The research lineage

This is not a Demo Day invention. The compact-steam-generator concept traces to 2010, when Prof. Koroush Shirvan at MIT proposed a compact steam generator to raise the power density of integral SMRs by 50%. Fifteen years of follow-on MIT work — CFD validation, NURETH conference papers, and Halimi's own doctoral research on SMR core design, scale economics, and high-burnup fuel under Shirvan — runs in an unbroken line to Apollo's 2026 spinout. Halimi co-authored the 2021 paper showing how compact heat exchangers cut $/kW for small PWRs.[36] [37] [38]

The validation path is equally institutional: an April 2026 research agreement with MIT's Department of Nuclear Science and Engineering tests both primary and secondary loops under conditions matching large commercial plants — generating the two-phase-flow and heat-transfer data that feeds directly into NRC licensing.[6]

Roadmap

Three reactors, each on a truck, each for a different customer.

A-10 for data centers, A-50 for industrial heat and small grids, A-300 for utilities — preceded by the A-0 demonstrator (built) and the A-1 MW-scale test facility this seed round funds.[2]

  1. 2026

    Built

    A-0 demonstrator

    Power
    Demonstrator
    Scope
    CSG · commercial PWR conditions

    Working demonstrator built and tested at MIT, reproducing commercial PWR temperatures, pressures, and water chemistry. Being shown at YC Demo Day; feeds the first NRC topical report.

  2. 2026 (target)

    Next

    Full-scale CSG demo

    Power
    Full thermal scale
    Scope
    Compact steam generator

    First full-scale demonstration of the compact steam generator — the single component that shrinks the whole plant. Validation data runs through the MIT NSE two-loop test collaboration.

  3. 2027 (target)

    Next

    A-1 facility

    Power
    ~1 MW
    Scope
    Multi-coolant test loop

    The $10M seed builds this. MW-scale multi-coolant testing — the same class of facility Radiant, Valar, and Aalo are building, after raising hundreds of millions each.

  4. 2028 (target)

    Future

    A-10

    Power
    10 MWe
    Scope
    Data center scale · on a truck

    First commercial product and the named subject of Apollo's NRC regulatory engagement plan (docket 99902160). Construction permit targeted for 2028.

  5. 2029 (target)

    Future

    A-50

    Power
    50 MWe
    Scope
    Small grid / industrial heat

    Mid-size module for industrial offtakers (chemicals, refining, heavy manufacturing) needing process heat or behind-the-meter power.

  6. 2031 (target)

    Future

    A-300

    Power
    300 MWe
    Scope
    Large grid · still on a truck

    Utility-scale power that remains truck-transportable. The next closest transportable competitor option is ~70 MW; most of the market is at ~10 MW.

NRC Licensing Path

Already on the docket — in the lane the NRC knows best.

Apollo filed its Regulatory Engagement Plan with the NRC on April 2, 2026 (ADAMS ML26092A282, pre-application docket 99902160) — publicly searchable, signed by Halimi, and specifically scoped to licensing the A-10. The plan targets a construction permit application by 2028.[5] [6]

Two topical reports on the steam generator technology are planned for submission this year, built on A-0 and A-1 test data. Because the CSG is the only novel component, the licensing surface area is a fraction of what an entirely new reactor type carries — the NRC has approved PWR physics dozens of times.[2]

The sober counterweight: prediction markets price a new-reactor license being granted in 2026 at just 24%. The EO-driven clocks are young, and the 2028 target leans on them holding. Apollo's hedge is design conservatism — when reviews drag, exotic designs wait longest.[40]

18 mo

EO 14300 cap on new-reactor decisions

12 months for license renewals

Apr 2026

Part 53 final rule effective

First tech-inclusive licensing framework

2028

A-10 construction permit target

REP docketed Apr 2026 (ML26092A282)

[5] [8] [11]

Supply Chain

The quiet moat: Apollo buys what competitors must invent.

Fuel is the field's single biggest hidden bottleneck.

Fuel. Most funded SMR challengers — Oklo, X-energy, TerraPower, Radiant, Antares — need HALEU, a fuel the US has produced roughly 920 kg of, total, against multi-tonne per-reactor needs. Domestic enrichment covers an estimated 10–25% of projected 2050 demand, and the shortage already pushed TerraPower's Natrium out two years. Apollo's standard low-enriched uranium ships commercially today from Framatome and Westinghouse.[26] [31] [32] [43]

Components. BWXT — sole manufacturer of nuclear components for the US Navy, with a $6B backlog — has a commercial agreement for pressure vessels. Siemens Energy supplies turbines; ABB and Framatome handle instrumentation and control. Nothing in the bill of materials requires a factory that doesn't exist.[34]

Turbines. Steam turbines carry a 2–3 year backlog — tight, but a different world from gas turbines, which GE Vernova expects to be sold out through 2030 with ~3-year lead times. Apollo's stated goal is compressing typical 5–10 year nuclear vendor lead times to 2 years for first delivery.[33]

Competitive Landscape

Everyone else is inventing a new reactor. Apollo is shrinking a proven one.

The funded field divides on one axis: exotic fuel/coolant combinations that need new supply chains, versus conventional PWR + standard LEU that doesn't. Apollo is nearly alone in the second camp at truck scale.

The exotic-fuel field has raised billions; Apollo's bet is $10M

Chart

Approximate total capital raised. TerraPower includes a $2B DOE award; X-energy includes its ~$1.1B April 2026 IPO. Orange = conventional PWR + standard LEU; gray = designs requiring HALEU, TRISO, sodium, or molten salt. Radiant, Valar, and Aalo are each building MW-scale test facilities comparable to Apollo's planned A-1.

Source · TechCrunch · TerraPower · TNW · DCD · Business Wire (2025–2026)

[23] [24] [27] [28] [30]

Apollo Atomics

A-0 built · REP docketed

Conventional PWR, standard LEU, light water. CSG is the only novel component. A-10 construction permit targeted 2028; 300 MW transportable ceiling no one else approaches.[5]

Radiant Nuclear

~$460M raised

1 MW portable HTGR (Kaleidos), TRISO HALEU fuel. First in line at INL's DOME test bed, targeting criticality by July 4, 2026. USAF microreactor delivery deal. Equinix-backed.[27]

Valar Atomics

$450M at $2B val

TRISO-fueled HTGR. Zero-power criticality at Los Alamos (Nov 2025) — billed as the first startup criticality under the DOE pilot, though skeptics note it was a zero-power assembly at a national lab.[28]

Aalo Atomics

$136M raised

Sodium-cooled, graphite-moderated 10 MWe Aalo-1 (5-packs to 50 MWe), purpose-built for AI data centers. Broke ground on Aalo-X at INL; cold criticality targeted July 2026.[30]

Oklo

Public · ~$14B cap

Sodium fast reactor, HALEU metal fuel, 15–75 MWe Aurora. First power targeted late 2027/early 2028 via DOE authorization (bypassing NRC for the first unit). Meta's 1.2 GW Ohio campus anchor.[21]

X-energy

IPO'd Apr 2026

80 MWe TRISO-HALEU pebble-bed HTGR. ~$2.9B raised including a ~$1.1B data-center-driven IPO; Amazon path to 5+ GW by 2039. Must also build and certify its own fuel plant (TX-1, target 2028).[23]

Kairos Power

Building Hermes

Molten-salt-cooled TRISO pebble bed. First non-LWR construction permit (2023); Hermes operational target 2027; Google's 500 MW partner. A test-reactor-first path years from commercial MWe.[17]

TerraPower

>$3.4B incl. DOE

345 MWe Natrium sodium fast reactor. First-ever commercial non-LWR construction permit (Mar 2026), building in Wyoming — but HALEU scarcity already cost it two years, and it's utility-scale, not transportable.[25]

Last Energy / Deep Fission

Conventional-fuel peers

The closest fuel-strategy analogs: Last Energy's site-built 20 MWe PWR-20 (30 planned in Haskell, TX) and Deep Fission's 15 MWe borehole PWR. Neither offers Apollo's factory-built 10–300 MW transportable range.[42]

NuScale / Rolls-Royce SMR

Utility-scale PWR

The proven-technology incumbents at 77 MWe (only NRC-certified SMR design) and 470 MWe (UK's selected technology, Wylfa). Stick-built utility deployments on 2030s timelines — not products for a single data center.[41]

Use already approved reactors, existing fuels, standard uranium, and regulatory pathways — and reduce the time to build from over 10 years to two.
Apollo Atomics launch video[4]

Founder Deep Dive

From our call with Assil and Drew.

On why incumbents haven't done this. Assil spent a decade inside EDF, Engie, and the Westinghouse/NuScale/Rolls-Royce orbit before founding Apollo. His answer is structural, not technical: the nuclear industry's change cadence is measured in decades. A new fuel-rod coating he worked on took 15 years to get approved. The legacy players have the engineering capability to build a compact steam generator — and organizational physics that make it nearly impossible to ship one.

On the design philosophy. Apollo's read on the new-entrant field (Kairos, TerraPower, Valar, Aalo) is that pursuing entirely new reactor types — sodium-cooled, molten salt, TRISO fuel — means re-deriving the entire validation, fuel, and supply chain stack at once. Apollo stays on proven PWR technology and changes only the steam generator: one novel component to test, one to license, everything else bought from qualified vendors.

On capital efficiency. The $10M seed is scoped to one deliverable: the A-1 MW-scale facility for multi-coolant testing in 2027. Assil's benchmark — Radiant, Valar, and Aalo are each building comparable 1 MW test facilities, having collectively raised well north of $300M.[27] [28] [30]

On the schedule's regulatory dependency. The team is explicit that the recent executive orders capping NRC licensing and design-approval timelines are central to hitting the 2028 construction permit. The mitigant they cite: every element of the design has been licensed before — the NRC isn't being asked to evaluate new physics, just a smaller heat exchanger.[8]

On manufacturing. Drew's mandate is compressing 5–10 year nuclear vendor lead times to 2 years. The agreements are already signed: BWXT for pressure vessels, Siemens Energy for turbines, ABB and Framatome for instrumentation and control. He flagged steam turbine availability (2–3 year backlog) as a genuine advantage over gas turbines, which he sees as severely constrained across the entire energy sector.[33] [34]

Founders & Team

Assil Halimi

Assil Halimi

Founder & CEO

A decade in nuclear before founding Apollo: advanced reactor designer on EDF's SMR team in France, reactor core physics at Engie (Belgium's nuclear operator), then a PhD in Nuclear Engineering at MIT under Prof. Koroush Shirvan — with work alongside Westinghouse, NuScale, and Rolls-Royce on PWR development. 15 peer-reviewed publications and 2 patents on reactor design and fuel optimization.

Drew Walker

Drew Walker

Repeat Founder

Co-Founder & COO

3.5 years at the White House running large events and operations, then scaled manufacturing at an electric truck company and co-founded Blue Innovations Group, an electric boat startup. B.A. in Political Science from George Washington University.

The early team also includes a head of manufacturing who spent ~2 years scaling battery manufacturing lines at Tesla and Rivian — and built Apollo's test reactor at MIT.

Risks & Mitigations

Risk

The core claims — a 20x smaller steam generator and 40x smaller plant — are company-reported and unverified pending independent validation.

Mitigation

The MIT NSE collaboration exists precisely to close this gap: full two-loop testing under prototypic commercial-PWR conditions generates the third-party heat-transfer and two-phase-flow data. Two topical reports on the steam generator go to the NRC this year, built on A-0 and A-1 test data.

Risk

The 2028 construction permit hinges on the NRC actually operating on its new 18-month clocks — a regime barely a year old and politically reversible.

Mitigation

Part 53 is a final rule (effective April 2026), not an aspiration, and the NRC is already running real reviews on 9–17-month schedules. Apollo's PWR + light water + standard LEU design sits in the most-precedented lane the NRC has — the agency has licensed this physics dozens of times.

Risk

Capital intensity: $10M is a small number in a field where Radiant, Valar, and Aalo have each raised $130M–$600M to build comparable MW-scale test facilities.

Mitigation

Apollo changes one component. Everything else — fuel, pressure vessels, turbines, instrumentation — is bought, not invented: Framatome/Westinghouse fuel off the shelf, BWXT pressure vessels under a commercial agreement, Siemens Energy turbines, ABB and Framatome I&C. Competitors' capital largely pays for new fuels, coolants, and supply chains Apollo doesn't need.

Risk

Incumbents (EDF, Westinghouse, Rolls-Royce) have the engineering depth to copy a compact steam generator if it works.

Mitigation

Assil spent a decade inside these organizations and his read is structural: the industry's change cadence is measured in decades — a new fuel-rod coating he worked on took 15 years to approve. Apollo holds the MIT research lineage (15+ years of compact-steam-generator work under Shirvan), 2 patents, and a startup's clock speed under a fast-licensing regime incumbents aren't organized to exploit.

Risk

Vendor lead times: nuclear-grade components typically quote 5–10 years; even steam turbines carry a 2–3 year backlog.

Mitigation

Lead-time compression is the COO's whole job — commercial agreements are already in place with BWXT, Siemens Energy, ABB, and Framatome, targeting 2-year procurement for the first reactor. Steam turbines are the right side of the scarcity: gas turbines are sold out through 2030, which pushes desperate data-center buyers toward exactly what Apollo ships.

What We're Watching

  • First full-scale CSG demonstration (2026 target) and the two NRC topical reports on the steam generator planned this year off A-0/A-1 test data.
  • Seed close → A-1 groundbreaking. The $10M is earmarked for the 1 MW multi-coolant facility targeting 2027 testing.
  • Movement on NRC pre-application docket 99902160 toward the 2028 A-10 construction permit application — and whether EO 14300's 18-month clocks survive contact with real reviews (Polymarket prices a 2026 new-reactor license at just 24%).
  • The DOE Reactor Pilot July 4, 2026 criticality race: how many exotic-fuel competitors hit their milestones, and whether the HALEU bottleneck (920 kg produced to date, against multi-tonne needs) reshapes capital flows toward conventional-fuel designs.
  • First customer LOI — a data center offtaker for the A-10 in the 2028–2035 deployment window the hyperscalers are all buying against.

References

  1. [1]Apollo Atomics — YC Profile
  2. [2]Launch YC — Apollo Atomics: The Modern Nuclear Company
  3. [3]Apollo Atomics — Company Website
  4. [4]Apollo Atomics — Let's Build It (launch video, May 2026)
  5. [5]NRC ADAMS ML26092A282 — Apollo Atomics Regulatory Engagement Plan for the A-10 (Apr 2, 2026, docket 99902160)
  6. [6]PR Newswire — Apollo Atomics Announces Research Collaboration with MIT's Department of Nuclear Science and Engineering (Apr 2026)
  7. [7]Glitchwire — Apollo Atomics Is Building Nuclear Reactors an Order of Magnitude Smaller Than Existing Plants (May 2026)
  8. [8]White House — EO 14300: Ordering the Reform of the Nuclear Regulatory Commission (May 23, 2025)
  9. [9]World Nuclear News — Trump sets out aim to quadruple US nuclear capacity
  10. [10]DOE — One Year After Executive Orders, US Nuclear Energy Renaissance Is in Full Swing (May 2026)
  11. [11]American Action Forum — New NRC Nuclear Reactor Licensing Rule (Part 53, final Mar 30, 2026)
  12. [12]NRC — Licensing Efficiencies (ADVANCE Act + EO 14300 implementation)
  13. [13]IEA — Energy & AI, Executive Summary
  14. [14]IEA — Energy & AI, Energy Supply for AI
  15. [15]Goldman Sachs — AI to drive 165% increase in data center power demand by 2030
  16. [16]Constellation — Crane Clean Energy Center: 835 MW, 20-year Microsoft PPA (Sep 2024)
  17. [17]Kairos Power — Google partnership to deploy 500 MW (Oct 2024)
  18. [18]POWER — Amazon backs 5 GW X-energy SMR deployment (Oct 2024)
  19. [19]Talen Energy — Amazon 1,920 MW Susquehanna PPA through 2042 (Jun 2025)
  20. [20]CNBC — Meta signs nuclear deals to power Prometheus AI supercluster (Jan 9, 2026)
  21. [21]Utility Dive — Meta nuclear deals with Oklo, Vistra, TerraPower
  22. [22]DOE — Initial Selections for New Reactor Pilot Program (Aug 2025)
  23. [23]TechCrunch — Nuclear startup X-energy raises ~$1B in data-center-driven IPO (Apr 24, 2026)
  24. [24]TerraPower — $650M fundraise incl. Nvidia NVentures (Jun 2025)
  25. [25]ANS — TerraPower begins construction on Natrium plant in Kemmerer (Apr 2026)
  26. [26]World Nuclear News — HALEU fuel availability delays Natrium reactor
  27. [27]DCD — Equinix-backed microreactor firm Radiant raises $300M
  28. [28]TNW — Valar Atomics raises $450M at $2B valuation
  29. [29]Gizmodo — California startup claims historic first in fission reactor milestone (Valar, Nov 2025)
  30. [30]Business Wire — Aalo Atomics secures $100M Series B for AI data center nuclear (Aug 2025)
  31. [31]NucNet — DOE extends Centrus contract to produce crucial HALEU (~920 kg to date)
  32. [32]Breakthrough Institute — Abundant Fuels for Abundant Reactors (HALEU supply gap)
  33. [33]Utility Dive — GE Vernova: ~80 GW gas turbine backlog, sold out through 2030
  34. [34]StockTitan — BWXT announces $1.4B in naval nuclear propulsion contracts
  35. [35]Wikipedia — Steam generator (nuclear power)
  36. [36]Nuclear Engineering and Design — The design of a compact integral medium size PWR (Shirvan et al., 2011)
  37. [37]Nuclear Engineering and Design — Impact of core power density on economics of a small integral PWR (Halimi & Shirvan, 2021)
  38. [38]MIT NSE — Assil Halimi: Working to Make Nuclear Energy More Competitive
  39. [39]DOE — COP28 Declaration to Triple Nuclear Energy Capacity by 2050
  40. [40]Polymarket — US grants license for new nuclear reactor in 2026?
  41. [41]Business Wire — NuScale 77 MWe SMR achieves NRC Standard Design Approval (May 2025)
  42. [42]ANS — Ten companies named for fast-tracked reactor pilots: what to know
  43. [43]Sightline — Low-enriched uranium could offer faster deployment of small reactors (Mar 2026)
  44. [44]Federal Register — NRC reviews of reactor designs previously authorized by DOE or Department of War (proposed rule, Apr 2, 2026)